It was quite a climb to the roof using home made ladders but the view was worth it, the Indian Ocean on one side and Tumaini on the other. We have now finished concreting all the ring beams that form the structural strength for the building, so next week we once again start putting up the trappers and mkoko’s in preparation for laying the roof slab in a couple of weeks.

Thanks for your prayers for our Form 4 KCSE students who started their final exams on Thursday with English, Maths and Geography. Keep praying; they still have 3 weeks to go yet!

Thanks Xx Glyn & Janey